Florida's Turnpike (SR91) Sumter Resurfacing
turnpike_sumter_2008-7-1004009.jpg
turnpike_sumter_2008-7-1004010.jpg
lineside.gif
When is the project over?
Description
This project was scheduled to last 240 calendar days. The Contractor gets additional days if they are unable to work due to weather. Presently we have added 3 weather days and the project is scheduled to last from 3/03/2008 to 10/28/2008.
New Advisories
turnpike_sumter_2008-7-1004004.jpg
turnpike_sumter_2008-7-1004011.jpg
turnpike_sumter_2008-7-1004005.jpg
FAQs
turnpike_sumter_2008-7-1004006.jpg
turnpike_sumter_2008-7-1004007.jpg
turnpike_sumter_2008-7-1004008.jpg
Contact Us
This project is to mill and resurface the Turnpike from MP 298 to MP 308, which is the last 10+ miles of the Turnpike Mainline system. There are also safety upgrades which include new guardrail, bridge retrofits, and new barrier walls to protect bridge columns.